Day 25: Radiator arrived, outside light added, dodgy plumbing and electrics!

Today we also had the plasterboard put on the walls using the dot and dab method.

Note that all the plumbing was replaced after these photos were taken – it was all done properly by a proper plumber.


Outside light installed

We also had an additional outside light wired up so the back is symmetrical.

It is look pretty good now. And the rain proved that it is all waterproof.

Oh, the radiator arrived today too. One big meaty one to heat the whole room from behind a sofa.

2013-08-15 17.37.34

Outside tap plumbed in

Outside tap plumbed in. UPDATE: My plumber removed all of this and re-plumbed the tap so it goes out through the kitchen wall, and not under the extension!

2013-08-16 16.11.46

UPDATE: the water pipe was removed completely

Light switch for the room

Light switch for the room

Electric cables down this gap, soon to be covered in slurry, insulation and screed

Electric cables down this gap, soon to be covered in slurry, insulation and screed

2013-08-16 16.24.25

Old extractor fan outlet and light cables

Old extractor fan outlet and light cables

2013-08-16 16.16.53

move

2013-08-16 16.17.30

move

Tap now outside where it belongs

Tap now outside where it belongs.
UPDATE – the tap is now around the corner, moved by my plumber

No idea what these numbers mean!

No idea what these numbers mean!

Various items keeping the plasterboard in place

Various items keeping the plasterboard in place

More like this in the House Extension section