House Extension

Removing top soil from site

Day 6: Excess Soil Removed From Site, Bricking Up Started The start of the second week, and we were on holiday. No photos. They took the soil down to level with the top of the foundations, apparently 6 skips needed (confirmed by a neighbour). It is amazing how much earth needs to come out of…

Trenches filled with the concrete foundation

Cement Lorry Arrived

Day 5: Foundations Completed – Trenches Filled With Concrete Day 5 was a major day. The pipes were boxed in and the trench tidied a little. At around 11.30am the cement arrived and the 3 builders started wheelbarrowing it from the road to the trenches at the back. The lorry ran out of cement and…

1.5 metre foundation trench completed

Day 4: Foundation Trench Dug To 1.5m Day 4 was both eventful and uneventful really. It was uneventful for me as nothing very visual happened, but very eventful for the builders who dug out an extra 50cm of rock hard earth. The builders dug out the rest of the trench, going down to 1.5m, which…

Digging Foundation Trenches

Day 2: Trenches Dug and Rainwater Drains Located Day 2: AM. Today the digger and skip arrived in the morning and the foundation trenches were started. The builders said that our soil is very hard and even the digger is struggling. I know all about that, having planted many trees over the years, and also…

Ground prep for a single story extension

Lines marked

Day 1: Ground Is Prepared and Marked Out For Foundation Trenches Day 1 – 15th July 2013 Building officially started today. I cleared the area last week and the ground is ready for the builders. However, they could not get their digger today, so the foundations will be started tomorrow. They marked out the extension…