1.5 metre foundation trench completed

Day 4: Foundation Trench Dug To 1.5m

Start of Day 4. Most of trench backfilled to get the digger into place.

Start of Day 4. Most of trench backfilled to get the digger into place.


Day 4 was both eventful and uneventful really. It was uneventful for me as nothing very visual happened, but very eventful for the builders who dug out an extra 50cm of rock hard earth. The builders dug out the rest of the trench, going down to 1.5m, which seemed more than twice as deep as 1m. Then the building inspector came out and gave it the all clear. They carried on digging some more and then went home.

The cement for the foundations is booked for 11am on Friday so there was not much to do in the afternoon once the trench was down to 1.5m, so everyone went home early.

Also, the rainwater run off pipes were cleared as they continue for more than 5m from the new boundary of the house.

Got some sneaky photos through the kitchen window of the builders working.

Deep Trench

Deep Trench

2013-07-19 07.39.10

Deep Trench

Deep Trench

2013-07-19 07.39.02 2013-07-19 07.38.56 2013-07-19 07.38.21 2013-07-19 07.38.17 2013-07-19 07.38.13 2013-07-19 07.38.08 2013-07-18 18.48.24

New pile of mud for the 3rd skip

New pile of mud for the 3rd skip

2013-07-18 18.48.00

The Digger

The Digger

2013-07-18 18.48.09 2013-07-18 18.47.56

2nd skip full. 3rd needed

2nd skip full. 3rd needed

A deeper trench

A deeper trench

2013-07-19 07.47.00

Builders working hard to deepen the trench

Builders working hard to deepen the trench

More like this in the House Extension section

Leave a Reply

Your email address will not be published. Required fields are marked *