It is not often during the extension that work was done at the weekend, but today was one of those days. The electrician had to devote most of a day to the second fit and could only fit us in on a Sunday.
The kitchen sockets were all completed, the oven, extractor fan, fridge and dishwasher all have a socket and an isolator switch. 4 spot lights / down lights were installed, and light switches added and moved. All that is left is to move the oven supply over to the RCD side when the new oven arrives – I think that is the final job (apart from disconnecting the old oven). Oh, and installing a heat detector too.
I was a bit slack with taking photos, probably because we were at a party for most of the day. It will look more impressive when completed though!