Loft Insulation Installed – Loft Week 7

Things really start coming together in week 7 when the even more insulation went in, and then the plasterboard started to go up.

The insulation used was QuinnTherm, which is similar to brands such as Kingspan and Celutex. For the roof, they put 75mm between the rafters and over-boarded with 25mm, to give 100mm total. All boards were sealed with insulation tape before insulation board was screwed to the rafters.


insulation and velux window ensuite window roof window insulation roof window and saw bedroom window dormer windows

plasterboarded roof plaster board goes up boarded ensuite boarded office